1.
|
05-28-12-139-1/25
|
“Ekoenergija” d.o.o, Brčko Distrikt BiH
|
Bulevar mira 8A, Brčko Distrikt BiH
|
25. 3. 2025
|
|
Permit for construction of power facilities with installed capacity exceeding 1 MW
|
Completing of the application
|
|
2.
|
05-28-12-143-1/24
|
“SE-Solar Energy” d.o.o., Zavidovići
|
Zlatnih ljiljana bb, Zavidovići
|
26. 3. 2025
|
|
Permit for construction of power facilities with installed capacity exceeding 1 MW
|
Completing of the application
|
|
3.
|
05-28-12-152-1/25
|
“Ekoenergija” d.o.o, Brčko Distrikt BiH
|
Bulevar mira 8A, Brčko Distrikt BiH
|
31. 3. 2025
|
|
Permit for construction of power facilities with installed capacity exceeding 1 MW
|
Completing of the application
|
|
4.
|
05-28-12-160-1/25
|
“Yavuz Company” d.o.o., Srebrenik
|
Ćehaje bb, Srebrenik
|
11. 4. 2025
|
|
Permit for construction of power facilities with installed capacity exceeding 1 MW
|
Completing of the application
|
|
5.
|
05-28-12-195-1/25
|
Renewable Energy Solutions BH doo Banja Luka
|
Miše Stupara 4, Banja Luka
|
13. 6. 2025
|
|
International trade in electricity
|
Determining the completeness of the application
|
|